Bolton, Perez & Associates
was responsible for the design and contract
documents, including South Florida Water
Management District (SFWMD) right-of-way
permit sketches for two bridge structures
within the Naranja Lakes Development. The
bridge below is the new 90-foot, 3-span
continuous concrete flat slab bridge
structure that carries Naranja Lakes
Boulevard over the C-103 Canal. The bridge
is founded on 18-inch pile bents supporting
a continuous 18” reinforced concrete deck
with span arrangements of 27-36-27 and
carries two traffic lanes with sidewalks,
one in each direction.
|
|